Metro asks safety oversight agency to do more extensive review of Silver Line

Metro asks safety oversight agency to do more extensive review of Silver Line

December 29, 2019
Last Mile Delivery Market Worth Observing Growth | UPS, FedEx, SF Express

Last Mile Delivery Market Worth Observing Growth | UPS, FedEx, SF Express

April 23, 2024
Top 5 Spend Analysis Software ranked in 2024

Top 5 Spend Analysis Software ranked in 2024

March 1, 2024
How Tesla And BMW Are Leading A Supply Chain Renaissance With Blockchain

How Tesla And BMW Are Leading A Supply Chain Renaissance With Blockchain

January 19, 2024
LATAM Cargo strengthens European cargo links

LATAM Cargo strengthens European cargo links

April 14, 2020
Ford making reusable hospital gowns from airbag materials as efforts against coronavirus expand

Ford making reusable hospital gowns from airbag materials as efforts against coronavirus expand

April 14, 2020
Don’t Sweat NBC’s Decision to Cut Back on Television Ad Inventory

Don’t Sweat NBC’s Decision to Cut Back on Television Ad Inventory

April 14, 2020
Software firms sharpen focus on AI, big data as IT spending drops

Software firms sharpen focus on AI, big data as IT spending drops

April 14, 2020
Navigating turbulent times in your supply chain (TL:DR version)

Navigating turbulent times in your supply chain (TL:DR version)

April 14, 2020
Last Mile Delivery by Drones Market is Booming Worldwide

Last Mile Delivery by Drones Market is Booming Worldwide

April 14, 2020
AIR CARGO MARKET SIZE, SHARE, DEMAND, TREND, LATEST INNOVATIONS & APPLICATION ANALYSIS AND INDUSTRY GROWTH FORECAST 2027 – Science In Me

AIR CARGO MARKET SIZE, SHARE, DEMAND, TREND, LATEST INNOVATIONS & APPLICATION ANALYSIS AND INDUSTRY GROWTH FORECAST 2027 – Science In Me

April 14, 2020
Wheat procurement in Patiala: 6,500 coupons issued to farmers – cities

Wheat procurement in Patiala: 6,500 coupons issued to farmers – cities

April 14, 2020
Pandemic, Plastics And The Continuing Quest For Sustainability

Pandemic, Plastics And The Continuing Quest For Sustainability

April 14, 2020
  • Supply Chain
  • Logistics
  • Warehousing
  • Procurement
  • Shipping
  • More
    • Strategic Sourcing
    • Spend Analysis
    • Inventory
    • Contact Us
No Result
View All Result
United States International Supply Chain Commission
United States International Supply Chain Commission
Home Procurement

Metro asks safety oversight agency to do more extensive review of Silver Line

by usiscc
December 29, 2019
in Procurement
0
Metro asks safety oversight agency to do more extensive review of Silver Line
492
SHARES
1.4k
VIEWS
Share on FacebookShare on Twitter

“As you know, there are many issues with the Project, including several material unresolved performance and construction deficiencies as detailed in the attached three letters that WMATA sent to the Airports Authority in September 2019,” Wiedefeld wrote in the letter, a copy of which was obtained by The Washington Post.

The accompanying letters document myriad concerns the transit agency has repeatedly raised about the second phase of the $5.8 billion rail project, which was expected to be completed in August, but now may not be finished until June 2020.

Safety commission officials said they are aware of Metro’s concerns.

“The WMSC has been extensively involved in oversight of Phase 2 of the Silver Line for over a year, even predating the WMSC’s certification,” commission spokesman Zachary Radford said. “We intend to keep up our efforts to ensure that [the Washington Metropolitan Area Transit Authority] commences operations only when all elements are ready for service and all hazards have been properly mitigated.”

As part of its role overseeing Metro safety, the newly certified WMSC is required to conduct an independent review of the Silver Line before it begins passenger service.

For more than a year, Metro and the Metropolitan Washington Airports Authority and its contractors have been at odds over how to resolve the project’s problems. MWAA is overseeing construction of the Silver Line, which when completed will be turned over to Metro to manage and operate.

MWAA officials said they remain committed to addressing Metro’s concerns.

“We’re continuing to work with everyone and will continue to have meetings during the holidays,” MWAA spokeswoman Marcia McAllister said.

Even so, Metro and MWAA and its contractors disagree on whether the problems present safety concerns for rail passengers.

“Multiple third-party experts who have evaluated the products and solutions for the panels and special track work all agree that there are no safety issues and that they meet the specified life expectancy,” said Keith Couch, project director for the Silver Line contractor, Capital Rail Constructors. He was referring to cracks in concrete structures and defective rail ties, two of many problems the project has had.

Wiedefeld, however, disputes that. “Although characterized by the Airports Authority and its contractors as future maintenance issues all four major deficiencies are at risk of being safety issues,” he wrote. “Accordingly it would be premature for the WMSC Board to approve the Safety and Security Verification Report (SSCVR) until the deficiencies are remediated to alleviate the risks.”

Wiedefeld emphasized that Metro will not accept responsibility for the rail line until it receives assurances of its safety from the Metrorail Safety Commission and the Federal Transit Administration.

Chief among the problems Wiedefeld has cited: defective rail ties that were manufactured with too much curvature and could cause trains to tilt outward when they move over those areas. The problem was first identified more than a year ago, but the parties have not been able to agree on a solution.

Metro wants CRC to replace the defective rail ties, but the contractor has refused, instead proposing several other solutions including using shims to level out the ties. Metro has rejected those remedies because they present difficult long-term maintenance challenges.

There are also issues with concrete panels that were installed at five of the six rail stations that are part of the project. An investigation determined that the concrete used for the panels did not meet project standards; they have a defect that could make them vulnerable to cracking.

“CRC has developed solutions that resolve the technical issues related to the concrete panels and special trackwork,” Couch said. “Extensive testing and engineering analysis has been performed on both components.”

Construction of the rail yard, which is being built by Hensel Phelps, has also been problematic. Metro inspector general Geoffrey Cherrington, who has been conducting his own evaluation of the project, said Metro’s consultants found there were too many small pieces of rock in the ballast for the track beds, which could cause drainage issues and cause the rocks to shift. If not fixed, the movement could cause tracks to shift as trains travel on them. In several management alerts issued in the fall, Cherrington urged Metro not to accept the project unless that and other issues were resolved.

Prematurely accepting the project, he said, “will create extraordinary cost, maintenance and operational issues early once WMATA takes ownership and control of this project. ”

The Silver Line is one of the biggest infrastructure projects under construction in the United States. The first phase of the 23.1-mile line opened in July 2014 with five stations — four in Tysons and one in Reston

Passenger service on the second phase, which will extend Metro service to Dulles International Airport and into Loudoun County, was originally scheduled to begin next month, but it probably will not begin until mid- to late 2020. Phase 2 is 11.5 miles long.

Share197Tweet123
usiscc

usiscc

  • Trending
  • Comments
  • Latest
Escape From Tarkov – How to Rotate Items

Escape From Tarkov – How to Rotate Items

February 5, 2020
Supply chain examination: Planning for vulnerabilities you can’t control

Supply chain examination: Planning for vulnerabilities you can’t control

December 7, 2019
Procurement Project Manager job with Camden London Borough Council

Procurement Project Manager job with Camden London Borough Council

February 17, 2020
Art Battle Wichita Falls III at The Warehouse, 1401 Lamar.

Art Battle Wichita Falls III at The Warehouse, 1401 Lamar.

0
Global Industry Analysis, Size, Share, Growth, Trends, and Forecasts 2016–2024 – ZMR News Reports

Global Industry Analysis, Size, Share, Growth, Trends, and Forecasts 2016–2024 – ZMR News Reports

0
PHOTOS: Ottawa firefighters respond to warehouse fire

PHOTOS: Ottawa firefighters respond to warehouse fire

0
Last Mile Delivery Market Worth Observing Growth | UPS, FedEx, SF Express

Last Mile Delivery Market Worth Observing Growth | UPS, FedEx, SF Express

April 23, 2024
Top 5 Spend Analysis Software ranked in 2024

Top 5 Spend Analysis Software ranked in 2024

March 1, 2024
How Tesla And BMW Are Leading A Supply Chain Renaissance With Blockchain

How Tesla And BMW Are Leading A Supply Chain Renaissance With Blockchain

January 19, 2024
  • Privacy Policy
  • Terms of Use
  • Disclaimer
  • DMCA
  • Contact Us

Copyright © 2024 United States International Supply Chain Commission (usiscc.org)

This website uses cookies to improve your experience. We'll assume you're ok with this, but you can opt-out if you wish. Cookie settingsACCEPT
Privacy & Cookies Policy

Privacy Overview

This website uses cookies to improve your experience while you navigate through the website. Out of these cookies, the cookies that are categorized as necessary are stored on your browser as they are essential for the working of basic functionalities of the website. We also use third-party cookies that help us analyze and understand how you use this website. These cookies will be stored in your browser only with your consent. You also have the option to opt-out of these cookies. But opting out of some of these cookies may have an effect on your browsing experience.
Necessary
Always Enabled

Necessary cookies are absolutely essential for the website to function properly. This category only includes cookies that ensures basic functionalities and security features of the website. These cookies do not store any personal information.

Non-necessary

Any cookies that may not be particularly necessary for the website to function and is used specifically to collect user personal data via analytics, ads, other embedded contents are termed as non-necessary cookies. It is mandatory to procure user consent prior to running these cookies on your website.

SAVE & ACCEPT
No Result
View All Result
  • Supply Chain
  • Logistics
  • Warehousing
  • Procurement
  • Shipping
  • More
    • Strategic Sourcing
    • Spend Analysis
    • Inventory
    • Contact Us

Copyright © 2024 United States International Supply Chain Commission (usiscc.org)