The Purpose of the Estimate

The Purpose of the Estimate

January 6, 2020
Last Mile Delivery Market Worth Observing Growth | UPS, FedEx, SF Express

Last Mile Delivery Market Worth Observing Growth | UPS, FedEx, SF Express

April 23, 2024
Top 5 Spend Analysis Software ranked in 2024

Top 5 Spend Analysis Software ranked in 2024

March 1, 2024
How Tesla And BMW Are Leading A Supply Chain Renaissance With Blockchain

How Tesla And BMW Are Leading A Supply Chain Renaissance With Blockchain

January 19, 2024
LATAM Cargo strengthens European cargo links

LATAM Cargo strengthens European cargo links

April 14, 2020
Ford making reusable hospital gowns from airbag materials as efforts against coronavirus expand

Ford making reusable hospital gowns from airbag materials as efforts against coronavirus expand

April 14, 2020
Don’t Sweat NBC’s Decision to Cut Back on Television Ad Inventory

Don’t Sweat NBC’s Decision to Cut Back on Television Ad Inventory

April 14, 2020
Software firms sharpen focus on AI, big data as IT spending drops

Software firms sharpen focus on AI, big data as IT spending drops

April 14, 2020
Navigating turbulent times in your supply chain (TL:DR version)

Navigating turbulent times in your supply chain (TL:DR version)

April 14, 2020
Last Mile Delivery by Drones Market is Booming Worldwide

Last Mile Delivery by Drones Market is Booming Worldwide

April 14, 2020
AIR CARGO MARKET SIZE, SHARE, DEMAND, TREND, LATEST INNOVATIONS & APPLICATION ANALYSIS AND INDUSTRY GROWTH FORECAST 2027 – Science In Me

AIR CARGO MARKET SIZE, SHARE, DEMAND, TREND, LATEST INNOVATIONS & APPLICATION ANALYSIS AND INDUSTRY GROWTH FORECAST 2027 – Science In Me

April 14, 2020
Wheat procurement in Patiala: 6,500 coupons issued to farmers – cities

Wheat procurement in Patiala: 6,500 coupons issued to farmers – cities

April 14, 2020
Pandemic, Plastics And The Continuing Quest For Sustainability

Pandemic, Plastics And The Continuing Quest For Sustainability

April 14, 2020
  • Supply Chain
  • Logistics
  • Warehousing
  • Procurement
  • Shipping
  • More
    • Strategic Sourcing
    • Spend Analysis
    • Inventory
    • Contact Us
No Result
View All Result
United States International Supply Chain Commission
United States International Supply Chain Commission
Home Procurement

The Purpose of the Estimate

by usiscc
January 6, 2020
in Procurement
0
The Purpose of the Estimate
494
SHARES
1.4k
VIEWS
Share on FacebookShare on Twitter

Like any industry, blame and accolades are an inevitable part of the electrical contracting business. I once heard someone say, “If you could buy people for what they are worth and sell them for what they think they are worth, you would be a millionaire.” Who knows, that might be an understatement — maybe make that a billionaire.

In my electrical contracting experience, when a project makes money, credit is usually chalked up to the project manager’s expertise. When a project loses money, the estimator is typically blamed for a bad estimate. The fact is the connection between estimating and project management is inseparable. The project manager would be out of a job without the estimator. This means a quality estimator and project manager are both necessary for a company to make a profit; therefore, both must share the blame for loss and the praise for success.

How does this work? The estimator must be accurate, and the project manager must be efficient. Accuracy, as well as efficiency, can be measured. Estimators should have benchmarks by which an estimate is analyzed to determine if it is accurate and correct. Following are some benchmarks that should be considered:

1. Labor hours per square foot — When tracking labor hours per square foot, the estimator will begin to see a pattern develop. This pattern will become predictable for similar projects. Labor hours per square foot of the current project being bid should be compared to similar project types previously bid.

2. Labor hours per device in all systems — i.e., lighting, branch, fire alarm.

3. Average length of conduit and wire or cable per device in all systems.

4. System with the largest percentage of labor — Projects are comprised of various systems, such as lighting, branch wiring, feeders, fire alarm, data, and generators. Depending on the type of project, the percentage of labor in each of these systems will vary from one project to another. For example, if the lighting system contains 40% of the labor and the fire alarm is only 5% of the total labor, a close review of the lighting system is necessary. 

5. Accurate material pricing — Both basic materials packages must be priced at market levels. Failure to maintain a method of keeping up with current pricing will increase the risk to minimize profits. 

6. Competitively quoted complete packages — Obtaining at least three quotations each for lighting fixtures, switchgear, and generators will help the contractor know that current market prices levels are being quoted. The contractor must maintain a good relationship with suppliers in order to receive competitive pricing. 

7. Total percentage of quoted packages of the total project costs.

8. Material items with the largest total costs — For some projects, 7% of the total number of items can account for 90% of the total material costs. For instance, a project with 230 electrical items in the estimate, 90% of the material costs may be comprised of only 16 items. The estimator must ensure accurate pricing has been included in the estimate for the items that comprise the largest percentage of material costs. 

9. Schedule vs. the crew size to determine supervision costs — The project schedule must be considered when determining the final price of a project. An accelerated schedule requires more workers, and workers must be supervised. Depending on the project, a full-time nonworking foreman may be required. 

Of course, these benchmarks will vary from project to project, especially between commercial projects, industrial projects, and correctional facilities. Just as an estimator has benchmarks to analyze accuracy, the project manager must have benchmarks to determine efficiency. Here are some benchmarks for the project manager:

• Time — How are we doing with the project schedule? The project schedule is controlled by the general contractor for most projects. Thus, the site foreman must monitor the project completion progress. If the schedule is not being maintained, this must be documented by the electrical contractor.

• Costs — Is the project under budget or the estimate?

• Percentage complete vs. percentage of total costs — When the percentage of total costs is greater than the percentage of the completion, a problem may exist. Tracking this comparison sooner rather than later is best. 

• Resources — How much time, staff, and equipment are you using? Are you committing too much in management without a return? Is there any unused rental equipment on the project that should be returned? 

• Scope — Is there scope creep or seep? Creep is uncontrolled or unauthorized changes. This occurs when the client wants work done at no costs. Scope seep is “allowed extras” without charge by the project manager. The project must be kept within the limits of the estimate.

• Performance — Are you meeting estimated labor units, including labor factors such as loss time, overtime, or multi-story effect? This includes performance of the general contractor. 

• Risks — Are the project risks being managed? The project manager must monitor any changes to the project’s schedule, work sequence, and staging areas. If these items are interrupted by the owner or general contractor, the electrical contractor should be entitled to compensation for additional labor and loss of labor productivity. 

• Quality — How is the quality or your work? Are electricians correcting and fixing unacceptable work due to poor planning and management? The project manager must provide the necessary information, materials, and tools for work that conforms to the contract documents. The contractor’s work is judged by these documents. 

At the end of the project, you should compare the estimator’s accuracy to the project manager’s efficiency. That way, you can truly know who should be praised and who should shoulder the blame. The real prize, however, is not in blaming or praising. It’s in the ability to arrive at solutions that enhance both the accuracy of estimating and the efficiency of project managing. When you stop placing blame and start seeking profit-making solutions, only then will you arrive at the true spirit of successful contracting — teamwork at its best.    

Kiper is an independent electrical estimating trainer and consultant based in Niagara Falls, N.Y. He can be reached at [email protected].

Share198Tweet124
usiscc

usiscc

  • Trending
  • Comments
  • Latest
Escape From Tarkov – How to Rotate Items

Escape From Tarkov – How to Rotate Items

February 5, 2020
Supply chain examination: Planning for vulnerabilities you can’t control

Supply chain examination: Planning for vulnerabilities you can’t control

December 7, 2019
Procurement Project Manager job with Camden London Borough Council

Procurement Project Manager job with Camden London Borough Council

February 17, 2020
Art Battle Wichita Falls III at The Warehouse, 1401 Lamar.

Art Battle Wichita Falls III at The Warehouse, 1401 Lamar.

0
Global Industry Analysis, Size, Share, Growth, Trends, and Forecasts 2016–2024 – ZMR News Reports

Global Industry Analysis, Size, Share, Growth, Trends, and Forecasts 2016–2024 – ZMR News Reports

0
PHOTOS: Ottawa firefighters respond to warehouse fire

PHOTOS: Ottawa firefighters respond to warehouse fire

0
Last Mile Delivery Market Worth Observing Growth | UPS, FedEx, SF Express

Last Mile Delivery Market Worth Observing Growth | UPS, FedEx, SF Express

April 23, 2024
Top 5 Spend Analysis Software ranked in 2024

Top 5 Spend Analysis Software ranked in 2024

March 1, 2024
How Tesla And BMW Are Leading A Supply Chain Renaissance With Blockchain

How Tesla And BMW Are Leading A Supply Chain Renaissance With Blockchain

January 19, 2024
  • Privacy Policy
  • Terms of Use
  • Disclaimer
  • DMCA
  • Contact Us

Copyright © 2024 United States International Supply Chain Commission (usiscc.org)

This website uses cookies to improve your experience. We'll assume you're ok with this, but you can opt-out if you wish. Cookie settingsACCEPT
Privacy & Cookies Policy

Privacy Overview

This website uses cookies to improve your experience while you navigate through the website. Out of these cookies, the cookies that are categorized as necessary are stored on your browser as they are essential for the working of basic functionalities of the website. We also use third-party cookies that help us analyze and understand how you use this website. These cookies will be stored in your browser only with your consent. You also have the option to opt-out of these cookies. But opting out of some of these cookies may have an effect on your browsing experience.
Necessary
Always Enabled

Necessary cookies are absolutely essential for the website to function properly. This category only includes cookies that ensures basic functionalities and security features of the website. These cookies do not store any personal information.

Non-necessary

Any cookies that may not be particularly necessary for the website to function and is used specifically to collect user personal data via analytics, ads, other embedded contents are termed as non-necessary cookies. It is mandatory to procure user consent prior to running these cookies on your website.

SAVE & ACCEPT
No Result
View All Result
  • Supply Chain
  • Logistics
  • Warehousing
  • Procurement
  • Shipping
  • More
    • Strategic Sourcing
    • Spend Analysis
    • Inventory
    • Contact Us

Copyright © 2024 United States International Supply Chain Commission (usiscc.org)